EHL will be presenting details of their proposed future phase Development on the Rear / Eastern Lands at Ebrington. A public Event is due to be held in September 2022. Once further details are available, info will be shared with all those who have previously registered their interest. Adverts will also be placed within local press. A Public event will be held, and plans displayed.

Progress

Planning - Overall Progress
Phase 3 Grade A Offices, Multistorey Carpark, Own Door Studios 50%
Initial Plan Development - Grade A Offices
Phase 3 Grade A Offices, Multistorey Carpark, Own Door Studios 100%
Discuss with DCSDC Planners - PAD 1
Phase 3 Grade A Offices, Multistorey Carpark, Own Door Studios 100%
Stakeholder Engagement
Historic Buildings, Roads, NI Water .... 50%
Public Engagement Event
September 2022 40%
PAD 2 - Design Progression and responses to Both PAD1 & Public Engagement
Target Autumn 2022 25%
Submission of Full Planning Applicaiton
October 2022
Expected Planning Approval
Q2 2023